The new signs along the south end of Cape San Blas sit on piles that rise 10 feet above the vertical survey datum. Each one has a white face, an orange border and two lines of text: "DANGER" and "SUBMERGED ROCK." That is the permitted design. Gulf County's project log shows the contractor still installing the last warning sign piles on August 10, 2026. On September 1 the log declared the 2025/26 St. Joseph Peninsula Beach Nourishment & Coastal Structures Project complete and reopened the Stumphole staging area to the public.
So this October is the first fall on the finished stretch. Very little of it stays put. According to the county's own project materials, the dry sand is supposed to get narrower. The rock structures offshore were set in sand and are expected to become visible underwater as that sand shifts. The beach between the Stumphole revetment and Scallop Cove looks its newest right now, and that look won't last.
What sits about 1.3 feet under the water
The project put roughly 830,000 cubic yards of sand along 1.1 miles of shoreline just north of the Stumphole revetment. It also built a row of eight submerged breakwaters, numbered SB-1 at the north end through SB-8 at the south. The U.S. Army Corps of Engineers permit modification dated April 17, 2026 describes them this way:
| Feature | Permitted design |
|---|---|
| Number of structures | 8, parallel to shore |
| Average length | 210 feet |
| Average width | 45 feet |
| Gap between structures | About 280 feet |
| Construction | Core stone under at least two layers of armor stone, at least 5 feet thick |
| Crest elevation | −2 feet NAVD88 |
| Water over the crest at mean low water | Roughly 1.3 feet |
| Seafloor covered | About 2.12 acres |
The last row of that table matters most to anyone who wades, paddles, casts from the surf or runs a small boat close to shore. At low tide, about a foot and a third of water covers the rock. One section of the biological opinion attached to the same permit describes the clearance as "roughly -1.0 feet." The documents don't agree on the exact figure, but they agree it is shallow.
The 280-foot gaps are there on purpose. The permit says the spacing allows "ingress and egress of aquatic organisms." The 2023 permit sketches drew the row roughly 200 feet seaward of the planned high-water line. The county has not posted an as-built survey of where the finished rocks ended up, so the signs are the best guide to where they are.
None of the project materials include recreation rules written specifically for the breakwaters. They don't address swimming, paddling, snorkeling or surf fishing around the structures. The marked piles are the official signal.
Why the dry beach is supposed to narrow
The county's project FAQ explains that a freshly pumped beach starts adjusting into a more natural shape almost immediately. Engineers call this "profile equilibration." The FAQ says the dry beach "will get smaller and will appear to quickly erode," and calls that intentional. The sand that leaves the dry beach moves to the nearshore sandbar just offshore.
That process also explains how the rocks will start to show. In July, WMBB reported on confusion among residents over whether the breakwaters would be buried or submerged. The Coastal Community Association looked into it and found that project documents show the structures set in the sand. According to that report, they "will naturally become visible underwater with erosion." As the sand settles, the rock row becomes easier to see under the water. The signs mark where it is long before that happens.
The sand color is changing too. Pumped sand goes down wet and looks darker than the existing beach. The FAQ says it dries quickly and keeps lightening over time. It came from offshore Borrow Area "F," the same source used for the 2019 nourishment, and was tested for color, shell content and grain size.
Why these rocks are underwater at all
The plan didn't start this way. A feasibility study completed in 2019 recommended three emergent T-head groins plus seven submerged breakwaters along roughly a mile of shoreline north of Stumphole. During permitting, review agencies preferred a design that would minimize impacts on swimming and nesting sea turtles and reduce erosion risk to the beaches on either side. The 2023 redesign replaced all ten of those structures with eight submerged breakwaters. Modeling for the redesign predicts the project will keep as much as 50 percent more sand on the beach after six years than nourishment alone would.
The county page also gives the baseline that pushed it toward structures. Between 2019 and 2023, more than 1.3 million cubic yards of sand eroded from the southern shoreline of St. Joseph Peninsula. The whole 2026 project placed about 830,000 cubic yards. So the new beach puts back less sand than those four years took away, and the breakwaters are meant to make it last longer than a nourishment project alone would.
Nourishment is still part of the long-term plan. The project page says periodic nourishment will continue, likely less often.
The stretch, south to north, by the markers the project used
The county's construction updates located the work by street address. Those addresses still work for finding your way along the finished beach:
- Stumphole revetment. This is the southern anchor of the project and the county's vehicle access point during construction. The staging area here reopened to the public on September 1, 2026.
- The 3500 block of Cape San Blas Road. This was the last stretch to get sand in late April, close to the revetment.
- 3775 Cape San Blas Road, the dome home. For several weeks this spring it marked the line between open beach to the north and the closed work zone to the south.
- 3967 Cape San Blas Road. Sand pumping started here first, and SB-1, the northernmost breakwater, sits offshore of it. SB-1 gave the contractor the most trouble. After several attempts, crews brought in more equipment and finished it on August 5.
- R-100, just south of the Scallop Cove store. This is the northern limit of the 1.1-mile fill.
The dune line along this stretch is new as well. Plantings of sea oats, panic grass and Gulf bluestem were finished on the rebuilt dune by June 8, 2026. Some owners may want to replace or reinstall a walkover over that dune. The county FAQ explains that any work on the beach and dune requires a permit from the Florida Department of Environmental Protection. Some walkovers can qualify for a field permit. Larger structures such as gazebos may need a Coastal Construction Control Line permit.
Bertha tested half of it, and Isaias is next
The structures have already been through one storm. In late July, with five of the eight breakwaters in place, Tropical Storm Bertha sent waves onto the Cape. Senior coastal engineer Joseph Morrow told WJHG that he hadn't heard of anything going wrong "at least where the breakwaters are currently in," and that "the beach seems to maintain a decent width." The same WJHG report described boardwalks washing away north of the project. Morrow said extending nourishment farther north is needed but lacks funding.
The design has limits. WMBB reported that the breakwaters are built to stay stable in waves up to five feet and that a large storm could affect them.
Tropical Storm Isaias is the first storm since the project was finished. Florida State Parks closed T.H. Stone Memorial St. Joseph Peninsula State Park and its overnight accommodations effective October 7, 2026. Gulf County Emergency Management's update at 9 p.m. on October 7 warned of wind, flooding rain, surge and possible tornadoes in the county. As of this writing, no one has published an assessment of the Stumphole reach after the storm or the current status of beach access. The county's emergency management page and the project site at sjpbeach.com are where those updates will appear.
The rest of October on and near the south Cape
The state park page still lists a Park After Dark program for October 10 from 7:30 to 9 p.m. Whether it happens depends on when the park reopens. On October 17, the Harvest Run 5K & Beer Mile starts at Scallop Cove General Store, at the north end of the project, with the 5K at 9 a.m. and the Beer Mile at 10 a.m. That same day, the Salt Air Farmer's Market runs in Port St. Joe, with later dates on November 7 and 21. The Blast on the Bay Songwriters Festival marks its 15th year in Port St. Joe from October 15 to 18. The 2026 Forgotten Music Festival has been canceled and won't be rescheduled this year.
The structures were designed with sea turtles in mind, and turtles are still on this beach's calendar. FWC lists the marine turtle nesting season in Gulf County as running through October 31, though most nesting is usually finished by September.
If you own on the south Cape or are thinking about a property between Stumphole and Scallop Cove, Chasity can walk the stretch with you. She can go over the dune line, walkover permits and the county's breakwater record for a specific address. Chasity Hill grew up on these beaches. Talk with Chasity to schedule a tour.
This article is general information, not legal, tax or financial advice. Consult a qualified professional about your situation.